You’re two weeks from hydrotest when your Authorized Inspector (AI, the third-party code inspector) halts the job. The supplier waived impact testing without a proper MDMT (minimum design metal temperature) justification under ASME Section VIII (the main pressure vessel code). Drawings, calcs, and weld procedures all have to be revisited. Production stops, the line stays cold, and leadership asks for answers. We’ve seen this more than you’d think. A small judgment call up front becomes a redesign, a reheat, and a reschedule.
And the safety stakes are real. Hydrostatic testing under UG-99 (the code’s hydrotest rule) runs roughly 1.3x MAWP (maximum allowable working pressure), so nobody gambles. When an NCR (nonconformance report) lands, it triggers more checks—material traceability, weld maps, and PWHT (post‑weld heat treatment) charts. We’ve watched one missed thermocouple record cascade into weeks of delay because AI calendars book out and CRN (Canadian Registration Number, provincial approval) reviewers ask for revised calcs.
So do you award to the lowest bid—or the lowest risk? We prefer the second, and we make it calculable. Our 5D framework, RFQ question bank, ITP (inspection and test plan), and scorecard let you hit code, budget, and schedule without surprises. Grab the scorecard to follow along; next, we’ll define what “right supplier” actually means.
As promised, let’s define “right supplier” in code terms so you buy safety and schedule, not drama. Under ASME Section VIII (pressure vessel design rules), Division 1 handles common designs; Division 2 covers higher stresses and fatigue. Suppliers must prove welding competence with Section IX procedures (WPS/PQR/WPQ—procedure, qualification, welder). You expect traceable materials (MTRs—mill test reports), correct calculations, proper code stamping (U or U2 stamp), and accurate data reports. Your role: set design conditions and service risks; their role: design, build, document, and certify.
Verification is non-negotiable. An Authorized Inspector (AI—the third‑party code inspector) witnesses hold points, reviews calculations, and signs the U-1 data report (vessel record). Expect disciplined documentation: weld maps tied to heat numbers, PWHT records (post‑weld heat treatment), calibrated gauges, and an MDR/data book that is built progressively, not backfilled. NDE (non‑destructive examination) must match service: RT/UT/MT/PT/VT (radiography, ultrasonics, magnetic particle, dye penetrant, visual) per acceptance criteria. Example: lethal service (toxic fluids) often drives more coverage and stricter joint efficiencies.
Working in Canada adds a provincial layer. You’ll need a Canadian Registration Number (CRN—provincial design approval) before fabrication or installation. Pick a lead province, submit calcs, drawings, and QA evidence, then pursue reciprocity across other provinces. Plan 6–12 weeks in the schedule.
When teams chase price or promises, the same failures repeat. These aren’t flukes—they’re predictable symptoms of weak capability and thin planning. Check your last project against these.
Generic procurement checklists reward polished brochures, not code evidence. In Section VIII (pressure vessel rules), competence looks like valid WPS/PQR/WPQ (weld procedures and quals), clean traceability, past U or U2 code stamps, National Board registration (NB—recorded data reports), and audit-ready data books. When engineering, QA, and purchasing don’t review the same artifacts, gaps hide until hydrotest. Example: purchasing accepts “RT included,” but engineering meant UT on Category B joints—resulting in rework and time lost.
Timing makes it worse. Long-lead items (heads, forgings, clad plate) get ordered before AI (Authorized Inspector) availability and hold points are locked, so changes become schedule killers. Generic RFPs miss Div 2 fatigue, MDMT (minimum design metal temperature) logic, or lethal service requirements, so suppliers price assumptions, not reality. The fix is a structured, evidence-based model that weighs design, documentation, shop capability, delivery, and total risk cost. That’s our 5D framework—up next.
If CRN and reciprocity were treated as afterthoughts on your last job, this is the fix. We use a 5D framework that forces evidence before promises: Compliance & Codes; Engineering & Manufacturing Capability; Quality & Testing; Project Management & Communication; and Total Cost of Ownership & Risk. ASME Section VIII (the pressure vessel design code) lives here, along with provincial CRN (Canadian Registration Number) pathways and National Board registration (central data reporting). Each dimension turns into checks you can see, score, and compare—so you don’t find out at hydrotest. On a recent Div 1 vessel, 5D flagged a missing impact‑testing rationale in week 2, not week 12. It’s practical. And fast.
Weight the 5D to match consequence of failure. Example: lethal service (toxic fluids) or low MDMT (minimum design metal temperature, e.g., −29°C) gets Compliance 30% and Quality 25%; a simple water vessel might flip more weight to Delivery. Acronyms you’ll see: AI (Authorized Inspector, the code inspector), ITP (inspection and test plan), NDE (non‑destructive examination), PWHT (post‑weld heat treatment), WPS/PQR/WPQ (welding procedure, procedure and welder qualifications), NCR/CAPA (nonconformance and corrective action), RACI (responsibility matrix), and LDs (liquidated damages in contracts). With shared definitions and clear weights, engineering, QA, and purchasing finally score apples-to-apples. Next, we’ll turn this into a sourcing process you can run this week.
| Dimension | What to verify | Evidence to request | Red flags |
|---|---|---|---|
| Compliance & Codes | Code stamping eligibility, Section VIII Division fit, provincial CRN pathways clarified | Current ASME certificates, sample U-1 data reports, recent code-stamped jobs with CRN numbers | Expired stamps, gaps since last audit, vague or shifting CRN strategy |
| Engineering & Manufacturing Capability | Similar builds, thickness ranges, materials (carbon, stainless, exotics), PWHT capacity proven | Equipment list, sample weld maps, sample calculations, capacity envelopes for rolling, forming, machining | We’ll figure it out later; outsourced critical steps without an oversight plan |
| Quality & Testing | ITP maturity, NDE scope, calibration controls, welder and procedure qualifications | ITP sample, WPS/PQR/WPQ library, NDE procedures, calibration logs, recent NCR/CAPA trends | Late NDE planning; missing WPS/PQR; backfilled data book at the end |
| Project Management & Communication | Dedicated scheduler, risk register, change control, escalation path, AI booking plan | Org chart, RACI matrix, sample recovery plans, real schedule with hold/witness points | Single-point dependency; generic Gantt; no hold points; no Authorized Inspector dates |
| Total Cost of Ownership & Risk | Costs beyond bid: logistics, rework, delays, expediting, CRN fees, warranty, LDs | Costed ITP, logistics plan, warranty terms, LDs clause, cashflow milestones | Lowest bid, unrealistic lead time, thin warranty, aggressive change-order posture |
You’ve got a scoring model; now let’s run it end‑to‑end. This 10‑step playbook de‑risks selection from market scan to kick‑off with engineering, QA (quality assurance), and procurement. Follow along—the RFQ (request for quotation) question bank comes next.
With your checklist and 5D scorecard, paste these into RFQs (request for quotation) and insist on evidence, not assurances. WPS/PQR/WPQ (weld quals), ITP (inspection plan), PWHT (post‑weld heat treatment), UT/RT/MT/PT (NDE), MDR (data book). Canada next: CRN timelines.
Those references and results matter even more if they include Canadian builds—because CRN (Canadian Registration Number, provincial design approval) and regulator reviews often set your critical path. Each province has its own authority: ABSA (Alberta Boilers Safety Association), TSBC (Technical Safety BC), TSSA (Ontario’s Technical Standards and Safety Authority), RBQ (Régie du bâtiment du Québec), and others. A CRN approves the design; it’s separate from fabrication. Plan 6–12 weeks for review, longer in peak periods or for Division 2 or exotic materials. The fix is to run CRN in parallel with engineering and long‑lead procurement, not after. We’ve guided teams through this without schedule slips.
Who does what? You, as owner/user, set design conditions and select the lead province. The engineer of record prepares calculations and drawings, including MDMT (minimum design metal temperature), corrosion allowance, and material specs; the fabricator supplies QA evidence and, post‑approval, completes the U‑1 (ASME data report) and stamping. Typical package: calculation report, drawings, forms, and quality program evidence. Choose a lead province, secure the number, then file for reciprocity—often 1–3 weeks after the first approval. Build it into your plan: submit at IFC minus 1–2 weeks, track comments within 10 business days, and freeze design before material release. With compliance mapped, we’ll lock your inspection and test plan (ITP) next.
Here’s the practical path we use: pick a lead province, pre‑check unique details, compile calcs/drawings/QA, submit, monitor comments, then pursue reciprocity. If you want the step‑by‑step, see how to get a CRN in Canada.
Working in Ontario? TSSA is exacting on MDMT rationale and materials evidence. Our TSSA registration Ontario guide covers forms, fees, and what reviewers look for so you plan realistic timelines.
Boilers and vessels both follow similar steps. For scope, paperwork, and timelines, start with boilers and pressure vessels CRN registration.
While we prep and track your CRN, we also lock your ITP (Inspection and Test Plan) so every check proves design assumptions, weld integrity, and safe operation. What gets tested, when, and to which standard? The matrix below spells it out.
| Test | Purpose | Typical standard/section | When used | Details |
|---|---|---|---|---|
| Hydrostatic pressure test | Validate structural integrity and leak tightness under test pressure. | ASME Section VIII UG-99 hydrotest requirements. | Most code-stamped vessels before U-1 signing and shipment. | See ASME hydrostatic pressure testing for pressures, holds, and acceptance. |
| Burst test | Determine ultimate failure pressure and safety margin for design validation. | Per R&D/QC qualification protocols; sometimes ASME code cases or OEM. | Prototype vessels, extreme service, or material/process qualifications before release. | Overview of burst testing, instrumentation, and failure mode capture. |
| Pressure piping testing | Verify integrity of connected piping systems and joints tied to the vessel. | ASME B31 series (e.g., B31.1, B31.3) per project scope. | On skids and packages where vessels integrate with pressure piping. | Plan pressure piping testing with media, pressures, and hold times. |
| Non-destructive examination (UT/RT/PT/MT) | Find surface and subsurface flaws per acceptance criteria and service risk. | ASME VIII, applicable code cases, and project specifications. | Per ITP for critical weld categories, joints, and repair verifications. | Record calibrations, technician certifications, coverage maps, indications, and dispositions. |
| Factory/Site Acceptance Test (FAT/SAT) | Prove functional performance, interlocks, and documentation readiness against requirements. | Project-specific FAT/SAT protocols and client witness criteria. | Before shipment at FAT; at site after installation for SAT. | Include alarms, instrumentation calibration, loop checks, and MDR (data book) completeness. |
Align test pressures, hold times, and acceptance with calculations and code. Capture signatures, charts, and results in the MDR (Manufacturer’s Data Report) for progressive turnover.
You’ve captured signatures and test charts in the MDR (Manufacturer’s Data Report); now turn that evidence into numbers. Set weights by risk, then score each supplier 0–5 on proof, not promises. Multiply, total, and compare for best value. Example: A 4.2 vs B 3.6 after weights. Next: red flags.
| Criterion | Weight (0–5) | Supplier A (0–5) | Supplier B (0–5) | Notes |
|---|---|---|---|---|
| Compliance & Codes | 5 | 4 | 3 | CRN (Canadian Registration Number) path clarity, valid certs |
| Engineering & Manufacturing | 4 | 4 | 3 | Similar builds, capacity envelope |
| Quality & Testing | 5 | 5 | 3 | ITP maturity, WPS/PQR (weld procedures/qualifications) |
| Project Mgmt & Communication | 3 | 3 | 4 | Schedule realism, clear escalation |
| Total Cost & Risk | 3 | 3 | 4 | Warranty, logistics, LDs (liquidated damages) |
With your scorecard open, what still stops the award cold? These signals correlate with rework, delays, and compliance failures. We’ve seen a missed thermocouple record add six weeks. If one appears, pause and verify before proceeding.
That last red flag—an underbid with a vague CRN plan—was exactly what we walked into on a Div 1 vessel in Canada. The project: ASME Section VIII Div 1 (pressure vessel code, common designs), MDMT (minimum design metal temperature) −29°C, CRN (Canadian Registration Number, provincial design approval) needed in three provinces, and an 18‑week deadline. Timelines were already slipping because the ITP (Inspection and Test Plan) was fuzzy and no lead province was chosen. We reset the RFQ (request for quotation): added a clear ITP outline, data‑book expectations, and an AI (Authorized Inspector) booking plan. Then we ran the 5D scorecard, shortlisted two shops, and requested a pre‑award coupon weld with NDE (non‑destructive examination) to validate heat input and technique.
In parallel, we picked Alberta as lead (ABSA—the Alberta Boilers Safety Association) and built a CRN package: calcs, drawings, materials, and QA evidence. Heads and forgings were ordered on early POs to protect schedule. We aligned UG‑99 (ASME hydrotest rule) with AI availability, locked witness/hold points, and issued a tidy MDR (Manufacturer’s Data Report/data book) index for progressive turnover. Results: lead‑province CRN in week 8, Ontario and BC reciprocity in weeks 10–11, coupon passed first time, and no NCRs (nonconformance reports) at hydrotest. FAT (Factory Acceptance Test) hit in week 17, and the data book was 90% complete by then. Delivery held at week 18 without overtime or change‑order drama.
The lesson is simple: disciplined selection and front‑loaded verification compress schedule and lower risk. When you require evidence up front—clear ITP, a defined CRN path, pre‑award tests, and a live MDR—you avoid rework, protect budget, and ship on time.
That disciplined, front‑loaded approach you just saw? We’ll help you apply it to your next vessel. We de‑risk supplier selection, map your CRN (Canadian Registration Number) path across provinces, and align ITPs (inspection and test plans) and data books so AI (Authorized Inspector) sign‑off isn’t a scramble. Nationwide support, fast. Start with a 30‑minute review call—bring your shortlist and dates, and leave with an action plan.
Let's discuss your test plan